Pangea Fullsize Updates

  • 11/15/24: First Update of Pangea Full-Size:
    • Orders all submitted to STR
    • Invoices Recieved
    • Invoices in the process of being paid by vendors
    • Production planning started
  • 12/13/24:It's been almost a month so here is a little status update:
    • Not much nothing has changed so far
    • Waiting for queue in production
    • Once production starts it should be pretty fast, but there are a lot of parts so things will finish at different paces
    • I'll continue to update as things progress!

  • 2/17/25: STR has returned from CNY and CNC processing is now underway
    • At the moment we are on track for the original timeline
  • 3/27/25: CNC is underway and expected to finish on April 20th. Surface finish is expected to finish on May 3rd. QC and packing is expected to finish May 13th for shipping to vendors!
  • 4/28/25: Anodizing testing is going well, surface finish may finish a bit later than the previous update. That being said, everything is looking good and progress is being made! I will provide a more accurate shipping to vendor timeline once packing is nearing completion! 

  • 5/12/25: There has been a delay reported by STR in completing Pangea fullsize. The issue stemmed from receiving poor quality materials for a different project that impacted the production schedule of many CNC projects. Pangea fullsize is expected to be completed with everything and packed for shipping to vendors on July 10th. 
    • The new ETA for bowl keyboards customers is late August 2025.